| Código U14ZMP020 | InfDes | Ud ud | Resumen POZO PREF. HM M-H D=80cm. h=2,50m. | CanPres | PrPres 383,50 | ImpPres | ||
| 1 | O01A030 |
| h. | Oficial primera | 3,500 | 13,42 | 46,97 | |
| 2 | O01A060 |
| h. | Peón especializado | 1,700 | 12,91 | 21,95 | |
| 3 | M07CG010 |
| h. | Camión con grúa 6 t. | 0,700 | 50,94 | 35,66 | |
| 4 | P01HC070 |
| m3 | Hormigón HA-25/P/40/I central | 0,265 | 59,57 | 15,79 | |
| 5 | P03AM070 |
| m2 | ME 15x30 A Ø 5-5 B500T 6x2.2 (1,564 kg/m2) | 0,780 | 1,64 | 1,28 | |
| 6 | A01MA020 |
| m3 | MORTERO CEMENTO M-15 | 0,001 | 83,91 | 0,08 |
| 7 | P02PH200 |
| ud | Anillo pozo mach.circ.HM h=0,50m D=800 | 1,000 | 25,93 | 25,93 | |
| 8 | P02PH230 |
| ud | Anillo pozo mach.circ.HM h=1,25m D=800 | 1,000 | 55,93 | 55,93 | |
| 9 | P02PH260 |
| ud | Cono mach.circ.HM h=0,6m D=600/800 | 1,000 | 52,12 | 52,12 | |
| 10 | P02PW010 |
| ud | Pates PP 30x25 | 8,000 | 7,78 | 62,24 | |
| 11 | P02AC380 |
| ud | Cerco/tapa FD/40 junta insonoriz.D=60 | 1,000 | 65,55 | 65,55 |
| Texto1 |
Pozo de registro prefabricado completo, de 80 cm. de diámetro interior y de 2,5 m. de altura útil interior, formado por solera de hormigón HA-25/P/40/I de 20 cm. de espesor, ligeramente armada con mallazo, anillos de hormigón en masa, prefabricados de borde machihembrado, y cono asimétrico para formación de brocal del pozo, de 60 cm. de altura, con cierre de marco y tapa de fundición, sellado de juntas con mortero de cemento y arena de río, M-15, recibido de pates y de cerco de tapa y medios auxiliares, sin incluir la excavación del pozo y su relleno perimetral posterior. |